AI Project Delivery Playbook

Phase gates

GateEvidenceExit decision
Problem validateduser workflow, baseline, value, ownerfund discovery / stop
Data feasiblesource, authority, quality, access, sampleproceed / narrow / stop
Technical feasibleprototype, baseline comparison, risksbuild / change / stop
Product definedPRD, scope, UX, metrics, acceptancecommit delivery baseline
Offline readyevaluation and hard gates passedoperational validation
Launch readysecurity, capacity, monitoring, rollback, supportcanary / hold
Canary acceptedonline quality, safety, cost, user outcomeexpand / rollback
Handover acceptedownership, runbook, SLA/SLO, maintenanceclose project

Do not commit full-scale scope and dates before critical feasibility evidence exists.

Work breakdown

Include work packages for:

Each package needs deliverable, owner, estimate/range, dependency, acceptance, and risk.

Estimation under uncertainty

Use three-point ranges for uncertain work. State assumptions. Isolate research/Spike work with a time box, question, method, budget, evidence, and decision. Add contingency based on identified risk, not arbitrary percentage alone.

Avoid treating “model quality” as a single task. Break it into dataset, baseline, experiments, error analysis, remediation, and regression.

RACI and decisions

Use one Accountable owner per outcome or decision. Clarify decision rights for scope, architecture, data use, residual risk, budget, model/vendor, launch, incident shutdown, and acceptance.

Do not make everyone Responsible or Accountable. Consult only roles whose expertise is needed; inform others asynchronously.

RAID

Write risks as “If [cause/event], then [impact].” Add probability, impact, trigger, prevention, contingency, owner, due/review, and status.

Change control

Require a change record when scope, milestone, budget, quality floor, model/vendor, data use, deployment region, autonomy, risk, or external dependency materially changes.

Show options:

Status reporting

Lead with outcome and evidence, then baseline variance, top risks/issues, next milestone, and decisions required. Use red/amber/green only with explicit definitions and recovery actions.

Acceptance and closure

Acceptance covers function, evaluation, safety/privacy, performance, cost, documentation, observability, rollback, support, training, vendor obligations, and ownership. Close only after open items have owners outside the project, financial/vendor closure is complete, assets are archived locally, and lessons/actions are recorded.

Recovery sequence

  1. Reconstruct facts and the current critical path.
  2. Identify root cause and remaining uncertainty.
  3. Quantify outcome, schedule, cost, quality, and risk impact.
  4. Generate feasible tradeoff options.
  5. Obtain a decision from the authorized owner.
  6. Rebaseline, communicate, and monitor recovery evidence.